Project Leader: Michael Compton
Project Description: Plan for future growth in the machine room (capacity planning).
Time Frame:
Deliverables
Responsibility Task Description Status
Compton/Young
Measure A/C, UPS, and power requirements
In Progress
with the present configuration.
Compton/Young
Identify the current capacity for A/C and power;
In Progress
determine the time the UPS can hold a charge
with the present configuration.
Compton/Young
Obtain cost estimates to upgrade the A/C, UPS,
Not Started
and power.